Short circuit test on Transformers;Why Short circuit test performed on HT side
Short-Circuit Test on Transformer
1. Purpose of Short-Circuit Test
-
To determine copper (I²R) losses of the transformer at full load.
-
To calculate the equivalent resistance and impedance of the transformer.
-
Performed on High-Voltage (HT) side (not LT) since rated current is much lower and easy to achieve.
2. Why Conduct Test on HT Side?
-
Rated current on HT side is lower than LT side.
-
Applying small test voltage (~5–6% of rated voltage) on HT winding produces rated current.
-
If performed on LT side, the HT winding would short to zero volts, causing dangerous high current and risk of winding damage.
3. Principle of the Test
-
Core losses are negligible (since applied test voltage is very small).
-
Wattmeter reading = copper losses at rated current.
4. Connection Diagram
-
Ammeter, Voltmeter, and Wattmeter connected on HT winding.
-
LT side short-circuited.
-
Variac (auto-transformer) used to gradually increase applied voltage until rated current flows in HT side.
5. Test Procedure
-
Short the LT side of the transformer.
-
Connect Ammeter, Voltmeter, Wattmeter on HT side.
-
Slowly increase applied voltage through Variac until ammeter reads rated current.
-
Record:
-
Applied voltage
-
Current
-
Wattmeter reading
-
6. Important Formulas
7. Numerical Example (2 MVA, 415 V / 11 kV Transformer)
Rated Current Calculation (3-phase):
-
On LT side (415 V):
-
On HT side (11,000 V):
š Hence, SC test is done on HT side (105 A) instead of LT side (2782 A).
8. Safety Notes
-
Never apply test voltage on LT while shorting HT → may cause excessive current & winding burn-out.
-
Always increase voltage gradually using Variac.
-
Ensure instruments (A, V, W) are properly rated for transformer capacity.
9. Key Takeaway
-
Short-Circuit Test is always performed on HT side because rated current is lower and easily achievable.
-
Wattmeter reading directly gives copper loss at full load.
Comments
Post a Comment