For a 100 gaj house (approximately 900 sq. ft. or 83.6 m²),generally concealed copper wiring system using FRLS (Flame Retardant Low Smoke) insulated wires, separate circuits for air conditioners and heavy appliances, and an appropriately rated distribution board (DB) with modern electrical protection to be used.
The following is a preliminary quantity and
cost estimate for a typical 2–3 BHK house with a kitchen, bathrooms, living
room, bedrooms, and a small utility area.
Important: The wire sizes and quantities
below are planning estimates. Final sizing depends on actual connected load,
circuit length, installation method, voltage drop, ambient temperature,
grouping, and the applicable electrical standards.
1. Assumptions for the Estimate
|
Particular |
Assumption |
|
Covered area |
100 gaj (900 sq. ft.) |
|
House configuration |
2–3 BHK, single floor |
|
Wiring method |
Concealed conduit wiring |
|
Conductor |
99.9% copper, FRLS insulated |
|
Supply |
230 V single-phase, subject to sanctioned
load |
|
Air conditioners |
3 split ACs |
|
Lighting points |
25 |
|
Ceiling fans |
5 |
|
6A socket points |
15 |
|
16A power points |
8 |
|
Geysers |
2 |
|
Kitchen heavy appliances |
Microwave, refrigerator, washing machine
and other appliances as applicable |
|
Distribution board |
Modular DB with MCBs, RCCB/RCBO
protection and surge protection as appropriate |
The estimate assumes that the house is
already constructed or being fitted out and that the work includes wiring,
conduits, accessories, and distribution-board installation. Major civil
repairs, plastering, painting and premium decorative fixtures are excluded
unless specified.
2. Recommended Wire Sizes for Different Appliances
Wire size should be selected according to
the actual load, current-carrying capacity, voltage drop, installation
conditions and protective-device rating. India's relevant reference standard is
IS 732:2019 — Code of Practice for Electrical Wiring Installations. BIS
|
Sr. No. |
Circuit / Appliance |
Recommended copper wire size for preliminary planning |
Suggested circuit protection* |
|
1 |
LED lights |
1.5 mm² |
6A or 10A MCB |
|
2 |
Ceiling fans |
1.5 mm² |
6A or 10A MCB |
|
3 |
General 6A sockets |
2.5 mm² |
10A or 16A MCB |
|
4 |
Refrigerator |
2.5 mm² |
Dedicated 16A circuit where appropriate |
|
5 |
Television and computer |
2.5 mm² |
10A or 16A MCB |
|
6 |
Washing machine |
2.5 or 4 mm² |
Dedicated circuit; rating based on
appliance |
|
7 |
Microwave oven |
2.5 or 4 mm² |
Dedicated circuit; rating based on
appliance |
|
8 |
1-ton split AC |
2.5 or 4 mm² |
Dedicated 16A/20A circuit, subject to
load |
|
9 |
1.5-ton split AC |
4 mm² as a planning provision |
Dedicated circuit; typically 16A/20A
subject to manufacturer requirements |
|
10 |
2-ton split AC |
4 or 6 mm² |
Dedicated circuit, sized by calculation |
|
11 |
2 kW geyser |
2.5 or 4 mm² |
Dedicated circuit; typically 16A, subject
to design |
|
12 |
3 kW geyser |
4 mm² |
Dedicated circuit; protective rating
based on design |
|
13 |
Kitchen heavy appliances |
2.5 or 4 mm² |
Separate circuits according to appliance
loads |
|
14 |
DB to room sub-distribution board, if
provided |
6 or 10 mm² |
Based on aggregate demand and route |
|
15 |
Main incoming supply |
10 or 16 mm² may be considered |
Based on sanctioned load, demand and
supply arrangement |
*These are indicative selections, not final
design ratings. The electrician must calculate the actual current, verify the
wire's derated ampacity, coordinate MCBs with the cable and account for voltage
drop and fault protection.
Buy House Wiring Kit by clicking at Image or Link
Special recommendations for AC wiring
For a typical house with three split ACs:
- Bedroom 1: Independent AC circuit.
- Bedroom 2: Independent AC circuit.
- Bedroom 3 / drawing room: Independent AC circuit.
- Provide a suitable isolator near each outdoor unit as required
by the manufacturer's instructions and applicable standards.
- Do not connect multiple ACs to one general-purpose socket
circuit.
- Keep an adequate earth conductor with each circuit.
Engineering recommendation: Do not select
AC wire size solely on the basis of tonnage. Check the nameplate current, rated
input, maximum operating current, cable length, installation conditions and
manufacturer's instructions before finalising the wire size.
3. Detailed Electrical Wiring Quantity Estimate
The following quantities are budgetary
estimates for a 900 sq. ft. house. Actual quantities can vary significantly
depending on the room layout, location of the DB, number of switchboards and
routing of concealed conduits.
A. Copper wire requirement
For estimating purposes, assume standard
90-metre wire coils. Quantities below represent the approximate combined length
of conductors in all required colours, including phase, neutral and earth where
applicable.
|
Sr. No. |
Wire size |
Estimated total length |
Equivalent 90 m coils |
Main application |
|
1 |
1.5 mm² copper FRLS |
900 m |
10 coils |
Lighting and fans |
|
2 |
2.5 mm² copper FRLS |
900 m |
10 coils |
General sockets and selected appliance
circuits |
|
3 |
4 mm² copper FRLS |
360 m |
4 coils |
ACs, geysers and heavy appliances |
|
4 |
6 mm² copper FRLS |
180 m |
2 coils |
Selected higher-load circuits/submain |
|
5 |
10 mm² copper FRLS |
90 m |
1 coil |
Main/submain wiring, if required |
|
6 |
4 mm² green/yellow earth conductor |
90 m |
1 coil |
Supplementary earthing and circuit
earths, as designed |
|
Total |
2,520 m |
28 coils |
Preliminary provision |
Important quantity note: The 2,520-metre
total is the sum of the conductor lengths, not the length of the physical cable
route. For example, a 20-metre route may require separate phase, neutral and
earth conductors. Earth conductors should be included in the actual circuit
take-off, and the additional 4 mm² earth provision above should not be treated
as a substitute for them.
The final purchase should be based on a
room-wise wiring layout and an actual site measurement. Do not order all coils
solely on the basis of this preliminary table.
B. Conduit, boxes and accessories
|
Sr. No. |
Material |
Estimated quantity |
Unit |
|
1 |
Heavy-duty PVC concealed conduit, 20 mm |
250 |
Metres |
|
2 |
Heavy-duty PVC concealed conduit, 25 mm |
75 |
Metres |
|
3 |
PVC junction boxes |
25 |
Nos. |
|
4 |
Modular switch boxes of various sizes |
20 |
Nos. |
|
5 |
Modular switchboards and plates |
20 |
Nos. |
|
6 |
6A switches |
40 |
Nos. |
|
7 |
16A switches and socket outlets |
8 sets |
Sets |
|
8 |
6A socket outlets |
15 |
Nos. |
|
9 |
Fan regulators |
5 |
Nos. |
|
10 |
Ceiling fan hook boxes |
5 |
Nos. |
|
11 |
Light/fan outlet boxes |
25 |
Nos. |
|
12 |
AC isolators/suitable local disconnectors |
3 |
Nos. |
|
13 |
Conduit bends, couplers, saddles and
accessories |
1 |
Lot |
|
14 |
Insulation tape, connectors, screws and
consumables |
1 |
Lot |
These quantities assume concealed conduit
installation. If the house has already been plastered, chasing, plaster repair
and repainting may add substantially to the cost.
4. Distribution Board (DB) and Protection System
For a house with three ACs, two geysers,
kitchen appliances and normal lighting loads, a properly designed distribution
board is essential.
Recommended DB specification
|
Sr. No. |
Component |
Preliminary specification |
Quantity |
|
1 |
Main distribution board |
18-way or 24-way modular DB, subject to
circuit schedule |
1 |
|
2 |
Main incomer |
DP main isolator, typically 40A/63A as
determined by load |
1 |
|
3 |
RCCB |
30 mA residual-current protection, with
suitable type and rating |
As designed |
|
4 |
RCBOs |
Individual overcurrent and residual-current
protection for selected circuits |
As designed |
|
5 |
MCBs |
Suitable ratings and breaking capacity
for each circuit |
As required |
|
6 |
Type 2 SPD |
Surge protection device, if required by
the installation's risk assessment and design |
1 set |
|
7 |
Neutral and earth bars |
Correctly rated and arranged |
1 set |
|
8 |
Earthing system |
Suitable electrodes/connections and
protective earth conductors |
As required |
Important: An 18-way or 24-way DB is a
starting point, not a confirmed requirement. Finalise its size after preparing
the circuit schedule. The main MCB rating must not be selected merely because
the house has three ACs.
A 30 mA RCCB/RCBO provides additional
protection against electric shock; it does not replace earthing or overcurrent
protection. Neutral conductors must be arranged correctly, and circuits
protected by separate RCBOs must not have their neutrals improperly
interconnected.
For Indian installations, refer to the
applicable requirements of the Bureau of Indian Standards (IS 732:2019)
and the Central Electricity Authority's safety regulations.
5. Electrical Load Estimate
The connected load of a typical 100 gaj
house may be estimated as follows. These are illustrative loads, not measured
appliance ratings.
|
Sr. No. |
Appliance |
Quantity |
Assumed load per unit |
Total connected load |
|
1 |
LED lights |
25 |
12 W |
0.30 kW |
|
2 |
Ceiling fans |
5 |
70 W |
0.35 kW |
|
3 |
Television |
2 |
100 W |
0.20 kW |
|
4 |
Refrigerator |
1 |
250 W |
0.25 kW |
|
5 |
Washing machine |
1 |
1,000 W |
1.00 kW |
|
6 |
Microwave oven |
1 |
1,500 W |
1.50 kW |
|
7 |
Geysers |
2 |
2,000 W |
4.00 kW |
|
8 |
Split ACs |
3 |
1,500 W |
4.50 kW |
|
9 |
Kitchen appliances and other sockets |
— |
Allowance |
2.00 kW |
|
Total illustrative connected load |
14.10 kW |
The actual connected load may be higher or
lower depending on the appliance ratings.
What does this mean for the electrical supply?
At 230 V, a 14.1 kW connected load would
draw approximately 61.3 A if all the loads operated simultaneously at unity
power factor. Actual current depends on the appliance characteristics.
For this reason:
- The sanctioned load and supply arrangement must be verified
with the electricity distribution company.
- A three-phase supply may be appropriate if required by the
calculated demand and applicable supply conditions.
- If three-phase supply is provided, the circuits must be
distributed across phases to balance the load.
- The main cable and protection devices must be selected using a
proper demand and fault-current calculation.
Do not assume that a 40A single-phase
supply is sufficient merely because the property is 100 gaj.
6. Approximate Electrical Wiring Cost Estimate
The following is an indicative budgeting
estimate for Delhi/NCR. Prices are approximate allowances, not verified
quotations from electrical contractors or manufacturers.
|
Sr. No. |
Description |
Estimated amount |
|
1 |
Copper FRLS wires of various sizes |
₹65,000–₹90,000 |
|
2 |
PVC conduits, junction boxes and
accessories |
₹12,000–₹20,000 |
|
3 |
Modular switches, sockets and switch
plates |
₹20,000–₹40,000 |
|
4 |
Distribution board, MCBs, RCCB/RCBOs,
isolators and SPD |
₹15,000–₹30,000 |
|
5 |
Earthing system and protective earth
wiring |
₹8,000–₹18,000 |
|
6 |
Fan boxes, connectors, lugs and
miscellaneous accessories |
₹5,000–₹10,000 |
|
7 |
Electrical installation and wiring labour |
₹35,000–₹55,000 |
|
8 |
Chasing, conduit laying and basic plaster
repairs |
₹10,000–₹20,000 |
|
Estimated total |
₹1,70,000–₹2,83,000 |
Recommended budget
For preliminary financial planning, keep a
budget of approximately ₹2.25 lakh for the complete basic electrical wiring
installation.
The estimate assumes ordinary modular
accessories and standard-quality materials. Premium switchgear, additional AC
circuits, concealed ceiling work, extensive civil repairs, decorative lighting
and other special requirements may increase the cost.
Items not included
The above estimate excludes:
- Purchase of air conditioners, geysers, fans and other
appliances.
- Decorative lights, chandeliers and premium LED fixtures.
- Inverter, battery and solar installation.
- Smart-home automation.
- Electrical meter and utility connection charges.
- Major plastering, painting and structural repairs.
- Additional floors, external landscaping or garden lighting.
- GST where applicable to the contractor's quotation.
Before approving a contractor's estimate,
obtain a detailed bill of quantities with make, model, wire length,
accessories, labour rates and GST clearly identified.
7. Recommended Circuit Schedule
For better reliability and easier fault
finding, avoid putting all appliances on a few common circuits.
|
Circuit |
Description |
Wiring provision |
|
C1 |
Living room and bedroom lights |
1.5 mm² copper |
|
C2 |
Remaining lights and fans |
1.5 mm² copper |
|
C3 |
General sockets in bedrooms |
2.5 mm² copper |
|
C4 |
Living room and TV sockets |
2.5 mm² copper |
|
C5 |
Kitchen general sockets |
2.5 mm² copper, subject to load |
|
C6 |
Refrigerator |
Dedicated circuit, where appropriate |
|
C7 |
Washing machine |
Dedicated circuit |
|
C8 |
Microwave and heavy kitchen appliances |
Separate circuits as required |
|
C9 |
AC in bedroom 1 |
Dedicated circuit |
|
C10 |
AC in bedroom 2 |
Dedicated circuit |
|
C11 |
AC in bedroom 3/living room |
Dedicated circuit |
|
C12 |
Geyser in bathroom 1 |
Dedicated circuit |
|
C13 |
Geyser in bathroom 2 |
Dedicated circuit |
|
C14 |
Spare circuit |
Provision for future requirements |
The final circuit arrangement may be
revised to suit the room layout, connected load and the applicable installation
standards.
8. Engineering Checks Before Handover
Before the installation is energised,
ensure that the contractor carries out and documents the following checks:
- Insulation resistance test: Verify insulation integrity of the
installed circuits.
- Continuity test: Verify continuity of protective conductors and
other required conductors.
- Polarity test: Confirm correct phase and neutral connections at
outlets and switches.
- Earthing verification: Check protective earthing continuity and
the earthing system's effectiveness.
- RCCB/RCBO testing: Verify operation using suitable test
equipment.
- Load and voltage-drop verification: Confirm that conductors and
protective devices are suitable for actual loads and circuit lengths.
- DB labelling: Label each circuit clearly for future
maintenance.
- As-built drawing: Obtain the final wiring layout and circuit
schedule from the contractor.
The applicable verification requirements
should be followed under IS 732 and the relevant electrical safety regulations.
BIS
9. Disclaimer
This estimate is prepared for preliminary
budgeting and planning purposes only. The quantities, wire sizes, circuit
arrangements, equipment ratings and costs are indicative and are based on
assumed requirements for a typical 100 gaj residential house.
The final design and estimate must be
prepared or verified by a competent electrical engineer after inspecting the
property, confirming the actual floor plan, appliance nameplate ratings,
sanctioned load, supply type, cable routing, installation conditions and
applicable statutory requirements.
All electrical work must be carried out by
an appropriately licensed electrical contractor, with suitable testing and
verification before energisation. Wire sizes and protective-device ratings must
not be finalised solely on the basis of this estimate. The actual cost will
depend on prevailing material prices, brands, site conditions, labour rates,
taxes and the final scope of work.
This document is not a substitute for a
site-specific electrical design, approved drawings or a certified electrical
safety inspection.