Buy Products here

Sunday, April 22, 2018

Types of Bushings and Voltage ratings

Bushings in Transmission Systems: Types, Classification & Applications

Bushings are one of the most critical components in transmission and distribution systems. Their primary role is to provide insulation between energized conductors and grounded parts, ensuring safe current transfer through transformer tanks, circuit breakers, switchgear, and other high-voltage equipment.

A failure in bushings can lead to catastrophic equipment damage, fire hazards, or extended outages. Hence, understanding their classification, design, and application is vital for electrical engineers and maintenance teams.




Classification of Bushings

Bushings can be classified into three main categories:

1.      Based on Insulating Material Used

2.      Based on Construction Type

3.      Based on Internal Insulation


1. Classification by Insulating Material

Bushings are often categorized based on the type of medium used for insulation:

·         Air-to-Oil Bushing – Air is used at one end, and oil at the other. Since oil has ~2x dielectric strength of air, the oil-side is shorter in length. Common in transformers.

·         Air-to-Air Bushing – Both ends insulated with air. Used in outdoor-to-indoor applications.

·         Air-to-SF₆ Bushing – Applied in SF₆ gas-insulated circuit breakers.

·         SF₆-to-Oil Bushing – Connects SF₆ bus ducts to oil-filled equipment.

·         Oil-to-Oil Bushing – Transition bushing between two oil-filled systems such as transformer-to-bus duct connections.


2. Classification by Construction

There are two construction types:

(a) Solid Type (Bulk Type) Bushings

·         Conductor with porcelain/epoxy insulation.

·         Used up to 25 kV, typical for distribution transformers, switchgear, and generator step-up transformers.

·         Limitation: Cannot withstand >90 kV at 60 Hz.

(b) Capacitance Graded (Condenser Type) Bushings

·         Used above 25 kV up to 1500 kV.

·         Multiple conductive layers embedded in oil-impregnated paper or epoxy.

·         Better electric field distribution and compact design.

·         More expensive due to complexity but essential for high-voltage equipment.




3. Classification by Internal Insulation

Depending on the insulating medium inside the bushing, they are further classified as:

1.      Air-Insulated Bushings – Used with air-insulated equipment; simple but limited in application.

2.      Oil-Insulated (Oil-Filled) Bushings – Mineral oil between conductor and insulation. Used in both solid and condenser bushings.

3.      Oil-Impregnated Paper (OIP) Bushings – Combination of oil and kraft paper, highly reliable for HV/EHV equipment.

4.      Resin-Bonded/Resin-Impregnated Paper (RBP/RIP) Bushings – Use resin instead of oil. RIP bushings are preferred in modern designs for reduced fire risk.

5.      Cast-Insulation Bushings – Solid cast epoxy material, robust and widely used in medium voltage systems.

6.      Gas-Insulated Bushings (SF₆) – Use pressurized SF₆ for insulation. Common in GIS and modern HV substations.


Bushing Interfaces as per IS 2099

High-voltage bushings (>1 kV) are designed as per IS 2099 standards. The standard defines five types of interfaces, based on mounting and contact type:

Interface

Contact Type

Current Rating (A)

1 Sec RMS (kA)

2 Sec RMS (kA)

3 Sec RMS (kA)

Peak Asym. (kA)

A1

Pin & Socket

250

12.5

9.0

7.5

31

B1

Pin & Socket

250

12.5

9.0

7.5

31

B2

Pin & Socket

400

16.0

11.3

9.2

40

C1

Bolted

630

28.0

19.7

16.1

70

C2

Bolted

1250

75.0

53.0

43.3

>150

D1

Bolted

800

50.0

35.3

28.8

125

D2

Bolted

1250

75.0

53.0

43.3

>150

F1

Bolted

2500

-

-

-

-

F2

Bolted

630

28.0

19.7

16.1

70

F3

Bolted

1250

75.0

53.0

43.3

>150


Applications of Bushing Types

A1 Interface Bushings

·         Used in oil-filled equipment like transformers, switchgear, capacitors.

·         Example types: 180AR-1 (12 kV, 250A), K180AR-1 (24 kV, 250A).

·         Also available as In-Air bushings for dry-type transformers, motors, and capacitors.

B Interface Bushings

·         Common for transformers and SF₆ circuit breakers.

·         Ratings: 12 kV / 400A to 36 kV / 400A.

Higher Interface Types (C, D, F)

·         Designed for high current, high voltage applications.

·         Bolted connections ensure mechanical robustness.

·         Widely used in EHV transformers, generator transformers, and high-capacity switchgear.


Conclusion

Bushings may appear as a simple connection device, but they are a critical link in high-voltage power systems. Their classification—by insulation medium, construction, or internal insulation—directly influences their application in transformers, switchgear, GIS, and other HV equipment.

For reliable operation, selection must consider dielectric strength, thermal performance, short-circuit withstand, and mounting interface as per IS 2099 standards. With the advent of RIP and SF₆ bushings, the industry is moving towards safer, maintenance-free, and more compact designs.

Wednesday, April 18, 2018

Electric Vehicle chargers and running cost of electric vehicles


Electrical vehicles seems to becoming reality as there is increased focus on reducing pollution and reducing dependency on petroleum products. But there are many challenges while going with electric vehicles such as time required for charging the vehicles and space required for parking the vehicles and also higher cost of electric vehicles in comparison to other vehicles. There is also challenge for long driving as while driving long charging of vehicles will be required after few intervals, which required considerable time for charging again. There is lot of infrastructure and electricity is required to cater all these problems.
Cost of driving electric vehicle is very low in comparison to petroleum products.

There are few terms you must know before going through in details:-
On Board Charging:-
There are chargers which are factory fitted and are known as on board chargers and there are 2 types of charging devices for the same:-
(i)                 Level-1 Charger:-
The slowest form of charging. Uses a plug to connect to the on-board charger and a standard household (120v) outlet. This setup provides between 2 and 5 miles per hour. While this does not sound at all impressive, it can work for those who travel less than 40 miles a day and have all night to charge.
(ii)               Level-2 Charger:-
Electric Vehicle chargers

These chargers converts alternating current (AC) power from the wall to Direct current (DC) power as batteries are required DC for charging. The speed of charging the vehicle varies most commonly there are following on board chargers:-
(i)                 6.6 kW on-board charger for battery electric vehicles
(ii)               3.3 kW on-board charger for hybrid electric vehicles
For faster charging off-board chargers are used.
These types of chargers use an EVSE to provide power at 220v or 240v at the output for upto 30 amps current. These chargers will charge the vehicle for upto 10-25 miles in an hour of charging at home or at a public station.


Electric Vehicle chargers


There is one another charging which is known as Level 3 charging and it is also known as DC fast charging. Usually these charges are similar to Gas filling dispenser sized machine.

There isn’t any single standard for fast charging of vehicles and Tesla well know name in the field of electric vehicles is using supercharger Network. Nissan Leaf is using CHAdeMO technique for faster charging. These fast chargers can charge 80% of vehicle within 30 minutes.

Costing for charging vehicles:-

Customers who are using the electric vehicles always prefer to charge vehicles at home and most often level 2 chargers are recommended.  These chargers are usually cost around $500-$600 depending upon the manufacturer. Depending upon the electricity cost charges will be applicable accordingly. In US there are incentives for both commercial and home chargers. Almost 30% of charging station cost is covered up by tax credits and other rebates given by government.
Nissan Leaf costs around $1 for every 25 miles which is very much lower cost than Petrol, Diesel and in-fact CNG or other Gasoline products.
Tesla Model S which can go upto 250 miles during complete charging and it will take around $10 for complete charging, which will cost around 25 miles per $1.
If you are using level 2 chargers at home which will charge vehicle on 8-9 hours than cost will be even much lower.

Time required for charging an electric car:-

Time required for charging electric cars is usually higher than filling up gasoline at fuel station, at fuel station it usually take 10-15 minutes in filling up fuel in vehicles. There are following details of vehicle which can run after one hour of charging with level 2 chargers:-
(i)                 Nissan Leaf: 11-22 miles
(ii)               Ford Focus Electric: 22 miles
(iii)             Volkswagen e-Golf: 24 miles
(iv)              BMW i3: 28 miles
(v)                Tesla Model S: 29-60 miles
(vi)              Chevy Volt: 11 miles

With DC fast charging of vehicle will be even faster details of the same as below:-
(i)       Nissan Leaf: 60-95 miles in 30 minutes
(ii)     Ford Focus Electric: (no fast-charging)
(iii)    Volkswagen e-Golf: 60-83 miles in 30 minutes
(iv)   BMW i3: 60-82 miles in 30 minutes
(v)     Tesla Model S: 170 miles in 30 minutes
With level 1 charger you can obtain four miles an hour, thus required lot of time for charging for electric vehicle.
There are following incentives and points to kept in mind while buying electric vehicles:-
(i)                 Know the incentives available:-
You should know what are the subsidies available in the market with e-vehicles. You must know the final price before buying vehicle, you must also know about maintenance cost and running cost of vehicle. You must compare running cost of vehicle with various fuels available in the market and know about buyback period of purchasing e-vehicle. There are lower charges offered by various power supply companies on power consumption for charging electrical vehicles which makes them even more economical.
(ii)               Get your electrical system ready for charging e-vehicle:-
Before installing the charging station you must know about ampere of charging station. You should install the charging station which can handle upto 30A for fast charging.
(iii)             Know about charging station near you:-
You must know about level 2 charging station near your job, park or regular stop. This will help you to charge your vehicle quickly when you are at work or relaxing somewhere.

 


Thursday, October 26, 2017

Three power calculations from single phase and three phase loads

Three-phase power — single-phase + three-phase loads explained (clean, compact & worked examples)

Key rules 

  • Power adds. Whether a load is single-phase or three-phase, its real power (kW) adds algebraically.

  • A statement like “three-phase load = 90 kW” means total three-phase real power = 90 kW (i.e., 30 kW per phase in a balanced system), not 90 kW per phase.

  • For balanced three-phase loads, you can convert total ↔ per-phase by dividing or multiplying by 3:

    • Pphase=Ptotal/3P_{\text{phase}} = P_{\text{total}}/3

    • Ptotal=3×PphaseP_{\text{total}} = 3 \times P_{\text{phase}}




Important formulas

Total three-phase real power (line-to-line voltage)

P3φ  (kW)=3  VL−L  I  PF1000P_{\text{3φ}}\;(\text{kW})=\dfrac{\sqrt{3}\;V_{L-L}\;I\;PF}{1000}

where VL−LV_{L-L} is line-to-line RMS voltage, II is line current (A), and PFPF is power factor.

Total three-phase real power (line-to-neutral / per-phase voltage)

P3φ  (kW)=3  VL ⁣− ⁣N  Iph  PF1000P_{\text{3φ}}\;(\text{kW})=\dfrac{3\;V_{L\!-\!N}\;I_{\text{ph}}\;PF}{1000}

where VL−N=VL−L/3V_{L-N}=V_{L-L}/\sqrt{3} and IphI_{\text{ph}} is phase current.

Single-phase apparent power and current (per phase)

  • Apparent power per phase (kVA): Sph=Ptotal3×PFS_{\text{ph}}=\dfrac{P_{\text{total}}}{3\times PF} (kVA per phase)

  • Phase current (A), using phase voltage VL−NV_{L-N}:

Iph=Sph×1000VL−N=Ptotal3×PF×VL−NI_{\text{ph}}=\dfrac{S_{\text{ph}}\times 1000}{V_{L-N}}=\dfrac{P_{\text{total}}}{3\times PF \times V_{L-N}}

Apparent power and PF reminders

  • Apparent power SS (kVA) = PP (kW) / PF.

  • For resistive loads PF ≈ 1. For induction motors PF ≈ 0.8 (full load typical) — values vary by machine and loading.


Worked numeric examples (step-by-step)

Example A — Using line-to-line voltage formula

Given: total three-phase real power P3φ=90 kWP_{\text{3φ}}=90\ \text{kW}, PF=0.8PF=0.8, VL−L=415 VV_{L-L}=415\ \text{V}.
Solve for line current II.

Use I=P3φ×10003  VL−L  PFI=\dfrac{P_{\text{3φ}}\times 1000}{\sqrt{3}\;V_{L-L}\;PF}.

Compute digit-by-digit:

  • 3≈1.732\sqrt{3}\approx 1.732

  • Denominator = 1.732×415×0.8=1.732×332=574.6241.732 \times 415 \times 0.8 = 1.732 \times 332 = 574.624 (approx)

  • I=90,000574.624≈156.5 AI = \dfrac{90{,}000}{574.624} \approx 156.5\ \text{A}.

So line current ≈ 156.5 A.

Example B — Per-phase view (same result)

Total P=90 kWP=90\ \text{kW} → per-phase real power Pph=90/3=30 kWP_{\text{ph}}=90/3=30\ \text{kW}.
Assume phase voltage VL−N=240 VV_{L-N}=240\ \text{V} (so VL−L≈415 VV_{L-L}\approx 415\ \text{V}).
Phase current Iph=Pph×1000VL−N×PF=30,000240×0.8=30,000192=156.25 AI_{\text{ph}} = \dfrac{P_{\text{ph}}\times 1000}{V_{L-N}\times PF}=\dfrac{30{,}000}{240\times0.8}=\dfrac{30{,}000}{192}=156.25\ \text{A}.

Matches Example A (rounding differences aside).


How to combine single-phase and three-phase loads

  1. Compute real power (kW) for each load (single-phase loads: P=V×I×PFP = V \times I \times PF; three-phase loads: use three-phase formulas above).

  2. Sum real powers to get total system kW: Ptotal=P3ϕ_loads+P1ϕ_loadsP_{\text{total}} = P_{3\phi\_loads} + P_{1\phi\_loads}.

    • Example: three-phase equipment = 90 kW, single-phase equipment spread across phases = 15 kW total → system total = 105 kW.

  3. If you need currents per phase, convert the total real power assigned to each phase to per-phase kW:

    • If single-phase loads are connected unevenly across phases, the system becomes unbalanced; compute each phase’s power/current separately and include neutral current by vector (or by arithmetic if you use magnitudes and phase angles).

  4. Neutral current: for unbalanced single-phase loads, neutral current is the vector sum of phase currents (can be significant if loads are unbalanced).

  5. Billing / demand meters: utilities typically measure total demand (kW/kVA) differently (e.g., three-phase demand meter), so you are billed on total demand — you won’t be billed 3× the total just because each phase carries some load. (But check local tariff rules for peak demand measurement method.)


Balanced vs Unbalanced — practical notes

  • Balanced assumption (equal load per phase): simplifies calculations by dividing by 3. Valid for large motors, balanced three-phase loads, and many industrial setups.

  • Unbalanced conditions (typical in domestic/commercial where many single-phase loads exist): you must compute per-phase currents from actual single-phase loads. Neutral currents and phase voltage drops become important; protection settings and conductor sizing must be verified for unbalance.

  • For accurate protection, conductor sizing, and harmonic analysis, treat the single-phase loads individually (don’t just divide totals by 3).


Short checklist for calculation

  1. Convert each load to kW (and note PF).

  2. Sum kW to get PtotalP_{\text{total}}.

  3. If you need line currents: use I=Ptotal×10003  VL−L  PFequivI=\dfrac{P_{\text{total}}\times1000}{\sqrt{3}\;V_{L-L}\;PF_{\text{equiv}}} where PFequivPF_{\text{equiv}} is either a known system PF or compute apparent power precisely.

  4. If loads are unbalanced, find per-phase kW and compute per-phase currents separately using Iph=Pph×1000VL−N×PFphI_{\text{ph}} = \dfrac{P_{\text{ph}}\times1000}{V_{L-N}\times PF_{\text{ph}}}.

  5. Check neutral current (vector sum of phase currents) and thermal limits.


Advantages of three-phase over single-phase (clean list)

  1. For a given power, three-phase machines are smaller and lighter.

  2. Three-phase motors are self-starting; single-phase often needs auxiliary start.

  3. Higher efficiency and typically better power factor for three-phase motors.

  4. Lower torque pulsation — smoother torque in polyphase systems.

  5. For transmission of the same power, three-phase requires less conductor material (more economical).

  6. Easier parallel operation of generators in three-phase systems.



Saturday, September 23, 2017

Working spaces for 600 V equipments installations (NFPA 70)

National Electrical Code (NFPA 70) – Working Spaces for 600 V Electrical Equipment

In electrical installations, providing adequate working space around electrical equipment is not just good engineering practice—it is a mandatory safety requirement under the National Electrical Code (NEC/NFPA 70). These provisions are designed to ensure safe operation, inspection, and maintenance of equipment rated at 600 Volts, nominal, or less.

This article explains the key working space requirements, exceptions, and clearances mandated by NEC for low-voltage electrical systems.




1. General Requirement for Working Space

  • Sufficient access and working space must be provided for safe operation, inspection, and maintenance.

  • Spaces must comply with NEC specifications regarding depth, width, and height.

  • No storage or obstruction is allowed in the designated working space.


2. Working Space Depth Requirements

(a) Minimum Depth

The minimum clear working distance depends on system voltage and conditions outlined in NEC Table 110.26(A)(1). Distances are measured from exposed live parts, the enclosure, or the opening if the parts are enclosed.

(b) Dead-Front Assemblies

  • Applies to switchboards, panelboards, and motor control centers (MCCs) where all live parts are accessible from the front only.

  • No working space is required at the back, unless rear access is necessary.

  • If rear access is required (non-electrical parts), at least 762 mm (30 in.) clearance must be provided.

(c) Low-Voltage Exception

For exposed live parts between 30 V RMS and 60 V RMS, working space clearance may be reduced—but only with special permission from the authority having jurisdiction (AHJ).

(d) Existing Buildings

When replacing equipment in older buildings:

  • NEC allows reduced clearance under Condition 2 of Table 110.26(A)(1).

  • Only permitted where strict maintenance procedures are in place (e.g., ensuring opposite equipment doors cannot be opened simultaneously).


3. Working Space Width

  • Clearance width = the width of the equipment or 762 mm (30 in.), whichever is greater.

  • Must allow at least a 90° opening of doors or hinged panels.


4. Working Space Height

  • Must extend from the floor or grade up to 2.0 m (6.5 ft) or the equipment height, whichever is greater.

  • Other equipment may project max 150 mm (6 in.) into this space.

Exceptions:

  1. Residential service equipment/panelboards ≤ 200 A may have less than 2.0 m height.

  2. Meters in sockets may project beyond equipment limits.


5. Clear Spaces (No Storage)

  • NEC strictly prohibits storage in required working space.

  • When normally enclosed live parts are exposed for servicing, temporary guarding must be provided if the space is in a passageway or open area.


6. Entrance and Egress Requirements

(a) Minimum Requirement

  • At least one entrance of sufficient size must be provided.

(b) Large Equipment (≥1200 A, >1.8 m wide)

  • Requires two entrances (each ≥610 mm wide and ≥2.0 m high) at opposite ends of working space.

  • A single entrance is allowed only if:

    • Unobstructed egress exists, OR

    • Working space depth is double the NEC minimum requirement.

(c) Personnel Doors

For equipment >1200 A within 25 ft of working space, doors must:

  • Open outward (in direction of egress)

  • Be equipped with panic bars/pressure plates for quick escape.


7. Illumination

  • Adequate lighting must be provided for all working spaces around switchboards, MCCs, and panelboards.

  • Lighting must not be controlled by automatic means only.


8. Dedicated Equipment Space

(a) Indoor Installations

  • Dedicated space = width and depth of equipment, extending 1.8 m (6 ft) above equipment or to structural ceiling.

  • No foreign systems (piping, ducts, leak protection devices) allowed in this space.

Exceptions:

  • Suspended ceilings with removable panels are permitted.

  • Sprinkler protection is allowed if installed properly.

(b) Outdoor Installations

  • Equipment must be in suitable enclosures.

  • Must be protected against accidental contact, vehicular traffic, or liquid leakage.

  • Clearance zone must remain unobstructed.


9. Locked Electrical Rooms

  • Locked rooms or enclosures housing electrical equipment are considered accessible to qualified persons.


Key Takeaways

  • NEC mandates strict depth, width, and height clearances for safe working spaces.

  • No storage is permitted in working zones.

  • Large equipment requires special egress provisions (panic bars, double exits, or extra depth).

  • Indoor and outdoor installations have dedicated clearance requirements.


✅ Disclaimer: This article provides a simplified explanation of NEC/NFPA 70 requirements for working spaces. Always refer to the latest NEC code and consult the Authority Having Jurisdiction (AHJ) for final compliance.



Saturday, September 16, 2017

National Electricity code,NFPA 70 for Examination, Identification, Installation, and Use of electrical Equipment

NFPA 70 (NEC) – Examination, Identification, Installation, and Use of Electrical Equipment

The National Electrical Code (NEC), NFPA 70, establishes mandatory rules to ensure the safe installation and use of electrical equipment. Below is a simplified breakdown of key requirements:


1. Examination of Electrical Equipment

Before approving equipment for installation, the following must be checked:

  • Suitability for purpose/environment/application (labeling, instructions, or listing).

  • Mechanical strength and durability of enclosures.

  • Adequate space for wire bending and connections.

  • Electrical insulation integrity.

  • Heating and arcing effects under normal and abnormal conditions.

  • Classification by type, voltage, and current rating.

  • Other safety factors relevant to user protection.




2. Installation and Use

  • Equipment must be installed as per listing or labeling instructions.

  • Voltage rating of equipment ≥ circuit’s nominal voltage.

  • Conductor material: Copper is standard unless otherwise stated.

  • Conductor sizes: Expressed in AWG or circular mils.

  • Wiring integrity: Free from shorts and ground faults.

  • Wiring methods: Only NEC-approved methods are acceptable.

  • Interrupting rating: Equipment must withstand fault currents safely.


3. Mounting and Cooling

  • Equipment must be firmly mounted, not on wooden plugs.

  • Natural ventilation must not be blocked; adequate clearance for heat dissipation is required.


4. Electrical Connections

  • Mixing of dissimilar metals (Cu-Al, Cu-Cu clad Al, etc.) must be avoided.

  • Fluxes and compounds must not harm conductors.

  • Terminals should be connected via pressure connectors, solder lugs, or hydraulic punching.

  • Splices must be mechanically secure before soldering and properly insulated.

  • Temperature limits: Conductor temperature rating must not exceed the lowest-rated component.


5. Equipment Provisions

  • Circuits ≤100 A: Only 60°C rated conductors unless listed for higher.

  • Circuits >100 A: 75°C rated conductors or higher with proper listing.

  • Separate connectors must not exceed their temperature rating.


6. Additional NEC Requirements

  • High-leg marking: Orange marking for high-leg in 4-wire delta systems.

  • Arc-flash hazard warning: Labels required on switchboards, panelboards, MCCs, etc.

  • Arcing parts: Must be enclosed/isolated from combustibles.

  • Markings: Manufacturer’s name, voltage, current ratings, etc. must be durable.

  • Disconnect means: Clearly marked for identification.

  • Series combination ratings: Must be visibly marked (engineered/tested).

  • Current transformers: Unused CTs must be short-circuited.

  • Available fault current: Must be field-marked and updated after modifications.

What You Can Do

  • Visit NFPA's Website: You can access the official NFPA 70 Standard (current edition and any Tentative Interim Amendments or errata) at the NFPA Document Information page. Simply go to www.nfpa.org/docinfo, search for NFPA 70, and download or view the figures as part of the standard. (Revize, NFPA)
  • Refer to the Official Handbook: The National Electrical Code® Handbook contains expanded commentary and annotated explanations with accompanying figures and diagrams.
  • Purchase or Access Through Subscriptions: Many institutions, organizations, or professionals subscribe to NFPA codes for legal compliance, training, and technical reference.

Quick Guide to Common Figure Types in NFPA 70

Figure Type

Typical Use

Enclosure and Equipment Layout

Demonstrates spacing, clearances, and mounting guidelines consistent with 110.26 and other requirements

Wiring Methods & Raceway Fill

Illustrates allowed conduit/busway fill percentages and conductor routing

Bonding & Grounding Diagrams

Shows proper connections in service equipment, sub-panels, and equipment grounding systems

Disconnecting Means Layout

Clarifies marking and visibility requirements per 100, 110, and disconnect provisions

Arc-Flash Hazard Marking

Visual placement for warning labels on panels and switchgear


Summary

  • NFPA 70 includes detailed figures accompanying various installation and safety requirements—but these diagrams are not freely accessible online.
  • You should obtain the actual standard or handbook through NFPA to view these figures.
  • NFPA’s official site is the most reliable avenue for accessing up-to-date figures, context, and explanatory material. (Revize, NFPA)

 


✅ In short: NFPA 70 ensures electrical equipment is properly tested, mounted, cooled, connected, marked, and protected against hazards like short circuits, arc flash, overheating, and mechanical failures.



Selection of Air Inflator for Vehicle

 The important point before purchasing Air inflator for Vehicle is that you should not select a tyre inflator only by its maximum PSI. You s...